Capital Project Work at SHS
June 05 2019 Update


Capital Project work will begin soon.
On Friday, June 7, an asbestos abatement contractor will be posting a memo on all SHS entry doors.  The posting, which is a state and federal requirement,  will state that asbestos abatement will be occurring within the school in the next 10 days.  All abatement work will take place in the gym, including the small gym.  Work will take place after hours and will not take place in any areas where students may be present.

On Saturday, June 15, the parking lot in front of the pool/sports complex will be fenced in and used as a contractor staging area for the capital project work that will occur over the summer.

May 05 2019 Capital Project Update to the Board of Education 